Sole Mia Miami FKA Biscayne Landings

In early 2015, ZEI was contracted by Oleta Partners to be the exclusive onsite concrete crushing and lake filling contractor at their 186 acres development called “SoleMia” located at 15055 Biscayne Blvd, North Miami, FL 33181. This site was originally a lime stone mine, then a Municipal landfill. Now it is South Florida’s biggest development with an estimated cost of 4 billion dollars. ZEI is contracted to receive Concrete Demolition, process it and crush it down to 6″ minus, then fill all existing lakes with that material. ZEI has successfully processed over 500,000 Cubic yards of concrete rubble and has filled in 7 out of the 8 lakes on their site. we are now working on filling the largest lake which is anticipated to require over 400,000 Cubic yards of Crushed concrete to fill.